(PALS)TILLICUM CREEK WATERSHED RESTORATION PROJECT
Project Overview
Basics
FHT-2020-00046
Not identified
Implementation
Activities include small tree thinning, pruning, handpiling, prescribed burning, shaded fuel break construction, closing roads, decommission roads, improve/upgrade roads on the Okanogan-Wenatchee National Forest.
5/12/2018
10/30/2024
U.S. Forest Service (USFS), USFS Silviculture (currently inactive) (Silviculture) (Inactive), USFS Hazardous Fuels (currently inactive) (Hazardous Fuels) (Inactive), USFS Timber Harvest (currently inactive) (Timber Harvest) (Inactive), USFS Completed Treatments from AGOL (USFS Completed Treatments from AGOL), USFS NEPA Boundaries from AGOL (USFS NEPA Boundaries from AGOL)
47526
Location
Contributing Organizations
Contractor Organizations | |
Lead Implementer | |
Partner Organizations |
Contacts
Primary Contact |
|
Funding
Expected Funding
$0.00
State, Federal, Other
Federal Legacy Roads program dollars, Washington State Legislative funding (via Good Neighbor Authority) for fuels reduction, and Yakama Nation investments in floodplain restoration have contributed to project implementation. Washington State DNR funding as linked to grants tracked in the Forest Health Tracker system are listed below.
2017-FHR-CAP 2017-2019 DNR Forest Hazard Reduction Capital - Yellowjacket GNA Non Commercial Fuels Project | $264,725.00 |
---|---|
2019-FHR-CAP 2019-2021 DNR Forest Hazard Reduction Capital - Federal Lands Investments GNA | $54,150.00 |
2021-2023-1168 2021-23 DNR HB 1168 Operating Funds | |
Total | $318,875.00 |
Agreements associated to this Project
Activities
Activities
Project Interactions/Events
Project Interactions/Events
Project Themes
Project Themes
Washington Department of Natural Resources utilized the Good Neighbor Authority to assist in implementation within this project. In state fiscal year 2020 2 contracts were awarded to Summitt Forestry for 956 acres of non-commercial fuels work, while an additional contract was awarded to Ecklund Excavation for 101 acres of non-commercial fuels reduction. Then, in the 2021-2023 state biennium funds were provided to implement House Bill 1168 through a GNA contract that completed 4,012 acres of non-commercial fuels work.
Project Details
Cost Share
Notes
No Notes entered.